Governor Evers approves US 14/61, WIS 27/82 and County T intersection improvements, Vernon County

Release date: May 9, 2023

To invest in Wisconsin’s transportation system, Governor Evers recently signed a $3.9 million contract to reconstruct US 14/61, WIS 27/82 and County T intersection, South of Viroqua in Vernon County. Preliminary work is scheduled to begin May 15.

James Peterson Sons, Inc. is the prime contractor for the project. The project is designed to improve the safety of the intersection by installing a roundabout.

The project will be constructed in stages to accommodate traffic during construction without detours.

Project completion is scheduled for early November 2023. The schedule is dependent on favorable weather conditions and construction progress.

For more information regarding traffic impacts, transportation news and improvement project updates in Wisconsin’s Southwest Region:

Motorists are reminded that using handheld cell phones in Wisconsin work zones is illegal. Alerts and updates provided via these sites are not intended for use while driving. When driving, your focus should always be on driving.

For more information, contact:

Hannah Punzel
WisDOT Southwest Region Communications
(608) 246-7907
hannah.punzel@dot.wi.gov