WIS 35 (Walnut Street to Pepin/Pierce County line), village of Stockholm to town of Stockholm - Pepin County

The Wisconsin Department of Transportation (WisDOT) is seeking public feedback on the below design proposal for construction on WIS 35 in Pepin County. The purpose of this outreach is to obtain your input on the identified needs and proposed improvements along WIS 35 between Walnut Street to Pepin/Pierce County line.

Location

The proposed improvement project is on WIS 35 from Walnut Street to Pepin/Pierce County Line in the village of Stockholm and township of Stockholm in Pepin County.

Purpose and Need

This 4.31-mile segment of WIS 35 is showing signs of deterioration. This project aims to extend the highway’s service life and reduce future maintenance costs and potential safety issues because of pavement failures.

Proposed improvements

  • Milling 2.25 inches of asphalt and overlaying WIS 35 with 3.75 inches of new asphalt pavement
  • Replacing guardrail
  • Rehabilitating culverts
  • No real estate acquisitions are planned

Schedule

Construction currently is scheduled for 2025.

Traffic Impacts

During construction, WIS 35 will remain open to traffic.

  • Single-lane closures will be used to complete the work with flagging operation.
  • Shoulder closures will be used for guardrail work.

Project Documents

The documents listed below are versions that were sent out in August/September 2021. Please note that the schedules in the handout and presentation have been revised. The new/current schedule is noted above.

In This Together program for businesses

WisDOT recognizes businesses located in work zones have special needs. It's critical that customers have access to businesses and that they continue to visit them, regardless of any road work inconvenience. WisDOT's In This Together program is offered to business and community leaders as an idea source as they plan for road construction in their area. On the In This Together, businesses can find:

  • Specially designed Business Coordination Guide for businesses to succeed during a highway construction project, includes information on:
    • Planning ahead
    • Staying informed
    • Keeping customers informed
    • Tips for businesses
  • Case studies that demonstrate techniques that have been successfully used in communities throughout Wisconsin.
  • Promotional samples showing a variety of examples of how businesses have promoted their businesses during construction.

During construction, temporary signing for business will be available. While signing and other marketing/advertising during the construction is up to the business, WisDOT encourages businesses to use the resources above to assist them with planning for construction before the construction begins.

Project Contacts

Paul Brauer, WisDOT Design Project Manager
(920) 492-5629
Paul.Brauer@dot.wi.gov

Dan Segerstrom, WisDOT Design Project Supervisor
(920) 492-7718
Daniel.Segestrom@dot.wi.gov