I-94 (County O to County EW), town of Millston and the towns of Grant and Lincoln and the village of Warrens - Jackson and Monroe counties

Location

Westbound I-94 between County O and County EW in the town of Millston in Jackson County and the towns of Grant and Lincoln and the village of Warrens in Monroe County.​

Overview

The pavement condition and other roadside features are showing signs of deterioration. To combat these, WisDOT is proposing:

  • Replacing select culverts and completing repairs/cleaning where required.
  • Adding stone to prevent erosion at the outlet at Rudd Creek.
  • Replacing guardrail and fence to meet current standards.
  • Installing ramp gates at County EW entrance ramps.
  • Replacing signing and installing new pavement marking.
  • Repairing select bridges including those over County O and over Aspen Avenue, County EW and over the railroad tracks.

Schedule

Construction currently is scheduled for 2026.

​Traffic Impacts

I-94 will remain open to traffic under bidirectional traffic along eastbound I-94.

  • Detours will be posted during County O and County EW ramp closures and during closure of County EW. County O is anticipated to remain open to one lane of traffic at all times.
  • Other local roads will offer motorists additional options for navigating around the work zone.

Contacts

​​Nicole Passuello
WisDOT Northwest Region Project Supervisor
(715) 833-5572
nicole.passuello@dot.wi.gov

Christena T. O’Brien
WisDOT Northwest Region Communications Manager
(715) 833-9814, (715) 828-9471
christena.obrien@dot.wi.gov

Wisconsin Department of Transportation
Northwest Region, Eau Claire Office
718 W. Clairemont Ave.
Eau Claire, WI 54701
(715) 836-2891, (800) 991-5285
nwr.dtsd@dot.wi.gov​​