Project overview

WisDOT has selected a preferred alternative for t a safety improvement at the intersection of US 151 and County DE. There is a history of right-angle crashes at this intersection, and it has qualified for federal Highway Safety Improvement Project (HSIP) funding.

Preferred alternative: Restricted Crossing U-Turn

WisDOT will build a Restricted Crossing U-Turn (RCUT) with offset right-turn lanes at the intersection. The alternative will reduce the number of conflict points from 42 to 12 and simplify decision making. Motorists will still be able to make all turning movements.

Schedule

Traffic impacts/detours

US 151 will be constructed in stages and remain open to traffic. County DE and Jackson Road will be closed or restricted to right-in and right-out during construction.

Status/phase

Design

Contact information

Amy Coughlin, P.E.
WisDOT Project Manager
(608) 245-5358
amy.coughlin@dot.wi.gov

Michael Bie
WisDOT Southwest Region Communications Manager
(608) 246-7928
michael.bie@dot.wi.gov

Wisconsin Department of Transportation (WisDOT)
Southwest Region, Madison Office
2101 Wright Street
Madison, WI 53704
Phone: (608) 246-3800
Fax: (608) 246-3843
TTY: 711
Email: swr.dtsd@dot.wi.gov