WIS 133 (Brewery Hollow Road to County N) - Grant County

Project location | Project overview | Public involvement | Schedule | Traffic impacts/detours | Status/phase | Contact information

Project location

WIS 133 (Brewery Hollow Road to County N), Village of Potosi - Grant County

Project overview

The roadway surface is aged and deteriorated with longitudinal and transverse cracking. Treatment is needed to extend the pavement service life.

This pavement replacement project will mill off 4.5-inches of the existing bituminous pavement and replace with 4.5-inches of new HMA pavement. The existing beam guard within the project limits will be replaced to meet current standards along with replacing 11 cross drain culvert pipes.

Public involvement

  • Spring 2024 - Public Involvement Meeting

Schedule

  • 2029 - Construction anticipated, advanceable to 2027 depending on funding

Traffic impacts/detours

WIS 133 will remain open to traffic during construction and the work is expected to be completed utilizing flagging operations. Road closures and detours are not expected for this project.

Status/phase

Design

Contact information

Derek Potter, P.E., 
WisDOT Project Manager
(608) 246-3861
derek.potter@dot.wi.gov

Hannah Punzel
WisDOT Southwest Region Communications Manager
(608) 246-7907
hannah.punzel@dot.wi.gov

Wisconsin Department of Transportation (WisDOT)
Southwest Region, Madison Office
2101 Wright Street
Madison, WI 53704
Phone: (608) 246-3800
TTY: 711
Email: swr.dtsd@dot.wi.gov