WIS 130 5770-01-02/71 -
Project description
- WIS 23 – Lone Rock, Wisconsin River Crossing, RICHLAND, SOUTHWEST
- Construction/replacement of 3 existing bridges across the Wisconsin River with 2 new bridges
- Schedule
- February 18, 2022 - Clarification Submittal #1 and One-on-One Meeting Agenda Deadline (5:00 pm Central Time)
- February 24, 2022 - One-on-One Meeting on RFP and ATCs
- March 4, 2022 DBE Meet and Greet
- March 4, 2022 - Clarification Submittal #2 and One-on-One Meeting Agenda Deadline (5:00 pm Central Time)
- March 10, 2022 - One-on-One Meeting on RFP and Initial/Final ATCs
- March 25, 2022 - ATC Submittal Deadline (5:00 pm Central Time) (see Note 2)
- April 1, 2022 - Department ATC Response Date
- April 8, 2022 - ATC Resubmittal Deadline (5:00 pm Central Time)
- April 8, 2022 - Final Clarification Deadline (5:00 pm Central Time)
- April 8, 2022 - SOQ Modification Request Deadline (5:00 pm Central Time)
- April 15, 2022 - Department ATC Final Response Date
- April 15, 2022 - Department SOQ Modification Request Response Date
- April 19, 2022 - Department Clarification Response Date
- May 12, 2022 - Proposal (Technical Proposal and Price Proposal) Due Date (3:00 pm Central Time)