Location
US 8, from Lustila Road to Tracy Road in Price, Lincoln, and Oneida Counties
Overview
The project includes performing a cold in place recycling (CIR) of the existing pavement surface and placing an additional two inches of new asphalt over the recycled pavement. Culvert pipes will be replaced in 14 locations. The culvert pipes at Scott Creek will be replaced with a two-cell box culvert.
Traffic Impacts
Motorists can expect minor delays during construction. The road will be open at all times and will utilize flaggers and temporary traffic signals.
Schedule
Local Officials Meeting: March 18, 2015
Local Officials Meeting: June 10, 2019
Local Officials Meeting: May 6, 2020
Public Involvement: June 2020
Complete project design: Fall 2021
Construction currently scheduled to begin: Summer 2024