Location
WIS 29, WIS 97 bridge and WIS 107 bridge, Marathon County
Project Overview
The existing bridge decks are experiencing cracking, patching, spalling and areas of delamination. The project involves the application of a new thin polymer overlay to each bridge.
Traffic Impacts
During construction, single lane closures are anticipated at both structures. At the WIS 107 bridge, work operations will keep to one side of the bridge. At the WIS 97 bridge, temporary signals will be used to maintain access. Additionally, temporary signals are also anticipated at the WIS 29 eastbound and westbound off-ramps.
Real Estate
No real estate acquisition anticipated
Schedule
Virtual local officials meeting - Aug. 2023
Public involvement mailing - Sept. 2023
Complete project design - Feb. 2025
Begin construction - Spring 2025