WIS 64 Resurfacing

This website contains information for three improvement projects scheduled for WIS 64 in Marinette County.

Construction is taking place in calendar year 2023 on one of the segments. For construction information on this and all projects under construction in the current year, please see the 511 Wisconsin family of construction project websites for construction operations, current traffic impacts, and any modifications to the schedule.

Northeast Region 511 Wisconsin construction website

WIS 64 resurfacing and culvert replacement (Project ID 9160-21-00)

WisDOT is in the process of developing plans for proposed improvements on 0.8 miles of WIS 64 in Marinette County. The purpose of the website is to provide information regarding the proposed improvements, describe the potential impacts it would have on the community, and offer an opportunity for public comment.

Project location

WIS 64 from 17th Road to US 141 near the village of Pound in Marinette County.


Project purpose and need

The purpose of the project is to extend the service life and improve the riding surface of WIS 64. Currently, the existing pavement is showing signs of deterioration including longitudinal and transverse cracking.

Proposed improvements

This is a resurface-level project. Proposed improvements include:

  • Mill two inches of the existing surface and pave two inches of hot mix asphalt
  • Culvert replacement
  • Pavement marking

Proposed schedule

  • Virtual Local Officials Meeting Summer 2022
  • Virtual Public Involvement Meeting Summer 2022
  • Final design plans for February 2025
  • Construction expected Summer/Fall 2025

Traffic impacts

WIS 64 will be closed for one week during the culvert replacement. Detour will follow County Road Q and County Road CP. WIS 64 will remain open to traffic for paving with lane closures and flagging operations.

Project public handout

WisDOT has created a public handout for this project. Please feel free to download, print, and share with anyone who does not have access to this website.

Public comments

The handout includes a prepaid mailer for public comments. You can provide comments in the following ways:

  • Fill out the comment form attached to the project handout and mail to WisDOT contact address.
  • Email comments or questions to the contact listed below
  • Call the contact below

Your comments assist us in developing a project that will serve the needs of the traveling public as well as the needs of the local community. Your input is welcome and appreciated throughout the design process.

Two, WIS 64 Marinette County-related projects

Below details two other improvement projects scheduled for WIS 64 between US 141 and US 180 in Marinette County. Each construction segment is identified by a separate Project ID below.

map

Western Project: WIS 64 from US 141 to County E (Project ID: 9160-17-00)

This project is located on 10.3 miles of WIS 64 from US 141 in the city of Marinette to County E in the towns of Grover, Pound and Beaver.

Project need and improvements

The pavement on this section of WIS 64 is deteriorating and culverts are in need of repair or replacement. WisDOT is proposing to place a new surface on the existing roadway to extend the pavement life of the roadway and provide an improved all-weather riding surface. Proposed improvements include:

  • Mill one inch of the existing pavement and overlay with two inches of asphaltic pavement
  • Widen paved shoulders from the existing three feet to five feet
  • Install centerline and shoulder rumble strips
  • Replace guardrail at the Little Peshtigo River Bridge
  • Replace the existing box culvert located approximately 1,100 feet west of County Q
  • Replace cross culverts at eight locations
  • Replace curb and gutter at the County W intersection
  • Resurface the Park-and-Ride at the County W intersection

Proposed schedule

  • Virtual Local Officials Meeting Summer 2021
  • Virtual Public Involvement Meeting Summer 2021
  • Final design plans August 2022
  • Construction expected Summer/Fall 2023

Proposed traffic impacts

  • WIS 64 will remain open for resurfacing operations using single lane closures and flagging operations.
    • Two lanes of traffic will be maintained when no construction work is taking place.
  • WIS 64 will be closed and detoured for two to three weeks for replacement of the box culvert. Access will be maintained to businesses and property owners in the work zone.

Right-of-way impacts/real estate

Temporary limited easements (TLEs) will be necessary for box culvert replacement. If your property will be impacted, a member of our real estate department will contact you.

Eastern Project: WIS 64 from County E to WIS 180 (Project ID: 9160-19-00)

This project is located on 7 miles of WIS 64 from County E in the town of Grover to just west of WIS 180 in the city of Marinette, Marinette County.

Project need and improvements

The pavement on this section of WIS 64 is deteriorating. WisDOT is proposing to place a new surface on the existing roadway to extend the pavement life of the roadway and provide an improved all-weather riding surface. Proposed improvements include:

  • Mill two inches of the existing pavement and overlay with two inches of asphaltic pavement
  • Widen paved shoulders from three to five feet width
  • Replace various cross culverts
  • Install centerline and shoulder rumble strips
  • Replace guardrail at the Peshtigo River Bridge and two box culverts
  • Replace wingwalls at the box culvert located at the County E/WIS 64 intersection
  • Replace curb and gutter at the WIS 180 roundabout

Proposed schedule

  • Local Officials Meeting Summer 2021
  • Public Involvement Meeting Summer 2021
  • Final Design Plans May 2022
  • Construction expected Summer/Fall 2024
    • Construction could occur in 2023 if funding becomes available.

Proposed traffic Impacts

  • WIS 64 will remain open for resurfacing operations using single lane closures and flagging operations.
    • Two lanes of traffic will be maintained when no construction work is taking place.
  • WIS 64 will be closed and detoured for approximately three weeks for replacement of the existing cross culverts along project. Access will be maintained to businesses and property owners in the work zone.

Right-of-way impacts/real estate

Additional right of way will not be required for this project. All work will be performed within the existing right of way.

In This Together program for businesses

WisDOT recognizes businesses located in work zones have special needs. It's critical that customers have access to businesses and that they continue to visit them, regardless of any road work inconvenience. WisDOT's In This Together program is offered to business and community leaders as an idea source as they plan for road construction in their area. On the In This Together website, businesses can find:

  • Specially designed Business Coordination Guide for businesses to succeed during a highway construction project, includes information on:
    • Planning ahead
    • Staying informed
    • Keeping customers informed
    • Tips for businesses
  • Case studies that demonstrate techniques that have been successfully used in communities throughout Wisconsin.
  • Promotional samples showing various examples of how businesses have promoted their businesses during construction.

During construction, temporary signing for business will be available. While signing and other marketing/advertising during the construction is up to the business, WisDOT encourages businesses to use the resources above to assist them with planning for construction before the construction begins.

Project contact

Kurt Vogel, P.E., Project Manager
WisDOT Northeast Region
944 Vanderperren Way
Green Bay, WI 54304
(920) 492-7706
Kurt.vogel@dot.wi.gov