Location
The project is on US 2/53 from 53rd Avenue East in the city of Superior to County C in the town of Amnicon, all in Douglas County.
Overview
The pavement and culverts carrying storm water on US 2/53 are showing signs of deterioration as is the pavement at Rest Area 23 along the eastbound lanes. To address these, the Wisconsin Department of Transportation is proposing the following:
- On US 2/53
- Making concrete pavement joint repairs and replacing concrete pavement panels.
- Milling the existing asphalt shoulders and overlaying the shoulders with new asphalt.
- Milling and overlaying side road connections and WIS 13 ramps.
- Installing shoulder rumble strips and completing gravel shouldering.
- Cleaning, repairing, lining or replacing culvert pipes.
- Resetting culvert pipe apron end walls and culvert sections.
- Repairing roadway slopes or embankments that have been eroded.
- Resealing construction joints on the concrete box culvert structure at Bear Creek and replacing the structure's wing walls on south side of US 2/53.
- Replacing the large signs on US 2/53.
- Replacing right-of-way fencing along entire project.
- Potentially adjusting guardrail.
- At Rest Area 23:
- Replacing existing exterior facility lighting.
- Upgrading and modernizing pedestrian curb ramps.
- Replacing select panels of sidewalk.
- Completing joints and crack cleaning on existing concrete pavement access and egress to the facility as well as perimeter parking lot.
- Repairing existing concrete pavement or replacing concrete panels as necessary.
- Repairing curb and gutter in spot locations.
- Overlaying existing concrete pavement with asphalt at entrance and exit to the rest area as well as perimeter parking lot.
Schedule
Construction currently is scheduled for 2028.
- Work could occur as early as 2026 or 2027.
Traffic Impacts
During construction:
- US 2/53 will remain open to traffic, but motorists might be limited to one lane in each direction.
- Delays should be expected when traveling through the work zone, especially during community hours.
- Rest Area 23 repairs might require closure of the facility.
Public Involvement
lease review the following materials for more information about the project:
Comments on the proposed work are being accepted through Sept. 30, 2023, by:
- Email: stephanie.king@dot.wi.gov
- Mail: Wisconsin Department of Transportation
1701 N. 4th St.
Superior, WI 54880
Attn.: Stephanie King
-
Comment form
Contacts
Stephanie J. King
WisDOT Northwest Region Project Leader
(715) 392-7874
stephanie.king@dot.wi.gov
Phil Keppers
WisDOT Northwest Region Project Manager
(715) 395-3027
philip.keppers@dot.wi.gov
Jeff Olson
WisDOT Northwest Region Project Supervisor
(715) 395-3032
jeffrey.olson@dot.wi.gov
Christena T. O'Brien
WisDOT Northwest Region Communications Manager
(715) 833-9814, (715) 828-9471
christena.obrien@dot.wi.gov
Wisconsin Department of Transportation (WisDOT)
Northwest Region, Superior office
1701 N. 4th St.
Superior, WI 54880
(715) 392-7925, (800) 590-1868
nwr.dtsd@dot.wi.gov