Location
The proposed project is located on WIS 137 between US 2 in the town of Eileen in east central Bayfield County and WIS 112 (Sanborn Avenue) in the city of Ashland in northwest Ashland County. It is approximately 4.8 miles in length.
Overview
The existing pavement on WIS 137 is deteriorated. To address that, the Wisconsin Department of Transportation is proposing to:
- Remove 2 1/4 inches of the existing pavement and place 3 1/4 inches of new asphalt on the roadway.
- Grade shoulders to match the new edge of asphalt pavement.
- Clean, repair or replace culvert pipes.
- Make guardrail improvements.
Schedule - Updated
Construction currently is scheduled for 2027 but could be advanced to 2024 if funding becomes available.
Traffic Impacts
During construction:
- WIS 137 will be closed, and traffic will be detoured via US 2.
- Access to residences and businesses will be maintained.
Contacts
Jeff Saxby
WisDOT Northwest Region Consultant Project Manager
(920) 380-2805
jsaxby@sehinc.com
Jeff Olson
WisDOT Northwest Region Project Supervisor
(715) 395-3032
jeffrey.olson@dot.wi.gov
Christena T. O'Brien
WisDOT Northwest Region Communications Manager
(715) 833-9814, (715) 828-9471
christena.obrien@dot.wi.gov
Wisconsin Department of Transportation (WisDOT)
Northwest Region, Superior Office
1701 N. 4th St.
Superior, WI 54880
(715) 392-7925, (800) 590-1868
WI Telecommunications Relay System (TTY): 711
nwr.dtsd@dot.wi.gov