Location
WIS 27 from WIS 29 in Cadott to Johnson Road on the south side of Cornell, all in Chippewa County.
Overview
The existing pavement is showing signs of deterioration. To address this and other issues, the proposed Wisconsin Department of Transportation project would:
- Remove 2 inches of the existing pavement and then overlay the road surface with 2 inches of new asphaltic pavement.
- Widen the paved shoulders from three feet to six feet from 80th Avenue/North Road to 350 feet south of Johnson Road.
- Replace the approaches and wing parapets on the west side of the Yellow River Bridge in Cadott.
- Replace the pedestrian underpass in Cadott.
- Extend the box culvert north of 135th Avenue in the town of Arthur and replace the structure's west wing wall.
- Brush the ends, clean and repair culverts in the project limits.
- Replace curb and gutter at spot locations.
- Upgrade pedestrian curb ramps on sidewalks.
- Replace guardrail.
- Place new pavement markings.
Schedule
Construction currently is scheduled for 2026.
Traffic Impacts
Motorists are expected to encounter:
- Lane closures controlled by flagging for road resurfacing.
- Lane closures controlled by temporary signals for bridge work.
- Shoulder closure for the box culvert extension.
- A detour for the replacement of the pedestrian underpass.
Contacts
Nathan Ulness
WisDOT Northwest Region Project Manager
(715) 563-4631
nathan.ulness@dot.wi.gov
James Koenig
WisDOT Northwest Region Project Supervisor
(715) 838-8391
james.koenig@dot.wi.gov
Christena T. O’Brien
WisDOT Northwest Region Communications Manager
(715) 833-9814, (715) 828-9471
christena.obrien@dot.wi.gov
Wisconsin Department of Transportation
Northwest Region, Eau Claire Office
718 W. Clairemont Ave.
Eau Claire, WI 54701
(715) 836-2891, (800) 991-5285
nwr.dtsd@dot.wi.gov