Project location | Project overview | Schedule | Traffic impacts/detours | Status/phase | Contact information
Project location
I-90/94 (US 12 to WIS 23), Wisconsin Dells - Juneau and Sauk Counties
Project overview
This project will repair existing interstate concrete pavement and place an asphalt overlay. Pavement in the interchanges at exits 85, 87 and 89 will also be improved.
Schedule
- Spring 2025 - Construction anticipated with possible advancement to 2024
Traffic impacts/detours
Short term lane closures, night work on the interstate. Construction on interchanges will be completed under flagging operations.
Status/phase
Design
Contact information
John Bainter, P.E.
WisDOT Project Manager
(608) 785-9729
john.bainter@dot.wi.gov
Michael Bie
WisDOT Southwest Region Communications Manager
(608) 246-7928
michael.bie@dot.wi.gov
Wisconsin Department of Transportation (WisDOT)
Southwest Region, La Crosse Office
3550 Mormon Coulee Road
La Crosse, WI 54601
Phone: (608) 785-9022
Fax: (608) 785-9969
TTY: 711
Email:
swr.dtsd@dot.wi.gov