Project location
US 12 (WIS 188/Tetiva Road Intersection), Sauk City - Dane County
Project overview
This is a safety improvement project. An intersection control evaluation analyzed several alternatives to improve safety and operations at the intersection. This evaluation included several alternatives such as two RCUTs (J turn and median U turn), a roundabout, and a signalized intersection.
Additional information:
Schedule
- October 6, 2022 - Public Involvement Meeting
- February 16, 2022 - Public Involvement Meeting
- Winter 2023 - Public Involvement Meeting
- Summer 2026 - Construction anticipated
Traffic impacts/detours
Depending on alternative chosen, US 12/WIS 188 intersection may be staged construction with lane closures or shoulder closures.
Status/phase
Design
Contact information
Cody Kammerzelt, P.E.
WisDOT Project Manager
(608) 243-5995
cody.kammerzelt@dot.wi.gov
Michael Bie
WisDOT Southwest Region Communications Manager
(608) 246-7928
michael.bie@dot.wi.gov