The proposed improvement project is on WIS 25 from WIS 35 north to Pleasant Ridge Road in the towns of Nelson, Maxville, Durand in Buffalo and Pepin Counties.
Purpose and Need
This 13.56 mile segment of WIS 25 is showing signs of deterioration. This project aims to extend the highway’s service life and reduce future maintenance costs and potential safety issues because of pavement failures.
Proposed Improvements
- Milling 3.5 inches of asphalt and overlaying WIS 25 with 3.75 inches of new asphalt pavement
- Adjusting guardrail
- Rehabilitating culverts
Proposed Schedule
- Final Design Plans: August 2023
- Bid Letting: November 2023
- Construction is currently scheduled for 2024
Traffic Impacts
During construction, WIS 25 will remain open to traffic.
- Single lane closures will be used to complete the work, and flaggers will direct traffic through the work zone.
Project Documents
In This Together program for businesses
WisDOT recognizes businesses located in work zones have special needs. It's critical that customers have access to businesses and that they continue to visit them, regardless of any road work inconvenience. WisDOT's In This Together program is offered to business and community leaders as an idea source as they plan for road construction in their area. On the
In This Together page, businesses can find:
- Specially designed Business Coordination Guide for businesses to succeed during a highway construction project, includes information on:
- Planning ahead
- Staying informed
- Keeping customers informed
- Tips for businesses
- Case studies that demonstrate techniques that have been successfully used in communities throughout Wisconsin.
- Promotional samples showing a variety of examples of how businesses have promoted their businesses during construction.
During construction, temporary signing for business will be available. While signing and other marketing/advertising during the construction is up to the business, WisDOT encourages businesses to use the resources above to assist them with planning for construction before the construction begins.
Contacts
Paul Brauer, WisDOT Design Project Manager
(920) 366-1097
Paul.Brauer@dot.wi.gov
Dan Segerstrom
WisDOT Northeast Region Project Supervisor
(920) 492-7718
Daniel.segerstrom@dot.wi.gov