Project overview
The Wisconsin Department of Transportation (WisDOT) plans to resurface 11.6 miles of WIS 130 between the west junction of County Highway B and WIS 154 to address deteriorating pavement conditions.
Improvements include:
- Mill and relay the existing pavement
- Overlay the asphalt base course with 3.5-inches of new asphalt pavement
- Replace guardrail and end terminals at two bridge structures
- Improve drainage in Bear Valley with grading, new storm sewer, and new culvert pipe
- Replace curb & gutter and sidewalk in Bear Valley
Schedule
- February 2022 - Public Involvement Meeting
- 2027 - Construction anticipated with possible advancement to 2026
Traffic impacts/detours
The road will be closed and detoured to through traffic during construction. Local traffic only.
Status/phase
Design
Contact information
Josh Koebernick, P.E.
WisDOT Project Manager
(608) 246-3859
joshua.koebernick@dot.wi.gov
Michael Bie
WisDOT Southwest Region Communications Manager
(608) 246-7928
michael.bie@dot.wi.gov
Wisconsin Department of Transportation (WisDOT)
Southwest Region, Madison Office
2101 Wright Street
Madison, WI 53704
Phone: (608) 246-3800
Fax: (608) 246-3843
TTY: 711
Email:
swr.dtsd@dot.wi.gov